Caltrans Logo

HOV Lane Gap closure

Description: In Riverside on Route 91 from Adams Street to 60/91/215 Interchange. Construct 2 HOV lanes (one in each direction). (TCRP #62)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Riverside
Zip Code 92501, 92504, 92506, 92507
 
Senate District
31
Assembly District 64
Congressional District 44
 
Caltrans District
08
 
 
County/State Route Riverside 91
Postmile Begin/End 15.6 21.6
Project Benefits
 Benefit Baseline Actual
Additional Auxiliary Lane Miles  3.6      
Daily Travel Time Savings (hours)  6771    6,430  
Lane Miles Added (HOV)  8.01    10  
Lane Miles Added (Mixed)  7.7    0  
Peak Period Time Savings (minutes)  494280    469,376  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Riverside County Transportation Commission John Standiford (951) 787-7141   jstandiford@rctc.org
Design (PS&E) Phase
Caltrans Wil Ochoa (909) 806-3200   wil_ochoa@dot.ca.gov
Right of Way Phase
Riverside County Transportation Commission John Standiford (951) 787-7141   jstandiford@rctc.org
Construction Phase
Caltrans Wil Ochoa (909) 806-3200   wil_ochoa@dot.ca.gov
 
Corridor System Management Plan
Caltrans John Pagano (909) 383-6327   john_pagano@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $0 $0
CMIA
$157,198 $-37,007 $120,191
Non-bond Funding
State/Federal*
$27,963 $0 $27,963
Local**
$47,616 $57,855 $105,471
Non Budgeted ETC
$0 $0 $0
 
Total**** $232,777 $20,848 $253,625

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$3,700 $-507 $3,193 $1,019
Design(PS&E)
$13,070 $7,192 $20,262 $20,071
Right of Way
$24,263 $45,255 $69,518 $53,809
Construction
$191,744 $-31,092 $160,652 $192,090
 
Total* $232,777 $20,848 $253,625 $266,990

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/30/2002 

12/31/2007 
 

 
04/30/2002 

08/30/2007 
100  04/30/2002 

08/30/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/30/2007 

02/02/2011 
 

 
08/30/2007 

06/30/2011 
100  08/30/2007 

06/30/2011 


Begin Right of Way Phase

End Right of Way Phase
06/01/2008 

08/01/2010 
 

 
11/01/2008 

03/01/2011 
100  11/01/2008 

03/01/2011 


Begin Construction Phase

End Construction Phase
06/01/2011 

06/01/2015 
 

03/01/2016 
02/10/2012 

11/30/2016 
100  02/10/2012 

08/31/2016 


Begin Closeout Phase

End Closeout Phase
08/01/2015 

08/01/2016 
 

 
03/19/2012 

07/13/2018 
100  03/19/2012 

12/01/2022 


-53 
Corridor System Management Plan
Adoption Date 05/01/2008    05/01/2008  100  03/01/2011  -34 
Implementation Date 06/01/2008    06/01/2008  04/01/2011  -34 
????????
Project Benefits
Benefit Baseline Actual
Additional Auxiliary Lane Miles 3.6
Daily Travel Time Savings (hours) 6771 6,430
Lane Miles Added (HOV) 8.01 10
Lane Miles Added (Mixed) 7.7 0
Peak Period Time Savings (minutes) 494280 469,376

Bond Funding Cost
Adopted:
$157,198,000
Current Approved:
$120,191,000
Actual Expenditures:
$119,800,608

 

Status as of December 31, 2023.